Recent Dilapidation Order Project

When this company was looking to close and relocate its headquarters, it turned to PD Industrial to control all aspects of the dilapidation and relocation process.
The Dilapidation Order involved the following works to be completed in four weeks
Office partitioning removal, including waste removal.
Pallet racking removal, barrier and steel removal.
Electrical stripout including on-site generators.
Furniture removal and Air-conditioning and sprinkler works
Our large team of fitters and experienced contractors were managed by our contracts department allowing the customer to concentrate on their relocation process.