  • Empty Warehouse

    Warehouse Re-Fit Project

    We have recently completed an entire warehouse re-fit as seen below. This eight-week project was carried out under CDM entirely controlled by PD Industrial Limited, and consisted of the following:- Removal of steel bar racking Building and floor clean Installation of access ramp and electric shutter door New pallet racking installed to SEMA regulated standards […]